Risk-based Erosion Control Planning
Dave Jenkins
Topic: In 2015, the Port of Seattle undertook the complete rehabilitation of the 16 Center/34 Center runway at SeaTac International Airport. Included in this project, scheduled for 180 days from April through October 2015, was the removal and full-depth replacement of the over 8,900 foot long, 150 foot wide, 18-inch-thick concrete runway, 50-foot-wide shoulders and blast pads, regrading, modification and reconstruction of taxiways, navigational aids, and storm, electrical and water utility upgrades.
Numerous project risks were identified and planned for early on. This presentation will discuss how risks were identified and how they were mitigated.
Learning Objectives:
• Understand the thought process that went into identifying project risks.
• Identify risk mitigation strategies on a large, multi-season, civil construction project.
• Gain new insights into ways to construct in a near zero risk tolerant environment.